During the storm system upgrade work carried out by Hazelwood Construction yesterday on Peninsula Road, the contractor encountered an unforeseen issue that required an immediate critical water shut-off to allow them to safely finish their work.  The shut-off should be brief, and work complete by 12 noon.

Reminder: water discolouration may persist as pressure resumes once the work is completed. Please note that properties surrounding the affected area may also see an impact during the noted time period. 
 
When conducting work on live infrastructure, impacts to the community often change as the situation unfolds. We thank the community for their patience as this necessary work is completed.
 
Hazelwood Contact Details:
 
Sue Bassett
Project Manager
Telephone: 250-716-1940
sbassett@hazelwood.ca

Pen Road Storm Crossing Waterline Shutdown